Dukovany Nuclear Power Plant – Habitability of Block and Emergency Control Rooms

KRÁLOVOPOLSKÁ RIA, a.s. executed the "Improvement of habitability of the block and emergency control rooms – ventilation systems for blocks 1 to 4" Project in Dukovany nuclear power plant.
The modified air-handling equipment is intended to provide the required atmospheric conditions in the block and emergency control rooms in case of an emergency situation.

 
Project:
Improvement of habitability of the block and emergency control rooms – ventilation systems for blocks 1 to 4
Project commencement:
8/2011
Locality:
CZ, Dukovany
Investor:
ČEZ, a.s. JE Dukovany
Scope of Project:
General delivery and installation. Preparation of the complete design documentation – mechanical and electrical parts, delivery and installation of the equipment for the air-handling systems reconstruction, ventilation system completing with the common emergency filtration unit and adaptation of the autonomous air-conditioning unit within the block and emergency control rooms of the nuclear power plant blocks 1 - 4.