Sludge Disposal after the Chemical WWTP

KRÁLOVOPOLSKÁ RIA, a.s., as a leading member of the „Sdružení KRÁLOVOPOLSKÁ  RIA - SMP CZ“ corporation, executed the "Equipment for the waste water treatment and for disposal of the sludge from the control basin and clarifier of the chemical WWTP  I" Project for the Mělník power plant. This Project was executed on a turn-key basis.

The system of slag discharge to the settling lagoon was also used for disposal of the waste water and sludge from the water service. The Project execution resulted in the separate system of waste water treatment, sludge treatment and service water recycling. The treated sludge in solid form is transported to the depot. The closed slag discharge system with recycled water utilisation enabled reduction of service water take-off from Labe river.

This Project has a positive impact upon the environment around the power plant and meets the quality requirements on the Mělník power plant effluents in compliance with the water regulations, thus improving water quality in the Labe river.

 
Project:
Equipment for the waste water treatment and for disposal of the sludge from the control basin and clarifier of the chemical WWTP I of the Mělník power plant
Project commencement:
3/2009
Locality:
CZ, Mělník
Investor:
ČEZ, a.s., Duhová 2/1444, 140 53 Praha 4
Scope of Project:
Complete delivery of the technological, civil and electrical parts of the Project „ Equipment for the waste water treatment and for disposal of the sludge from the control basin and clarifier of the chemical WWTP I “ on turn-key basis, consisting of the preparation of design documentation, delivery, installation, testing, startup and personnel training.