WWTP Kobylí, 2 420 PE, Břeclavsko Project, Part C

KRÁLOVOPOLSKÁ RIA, a.s. executed the reconstruction of the mechanical and biological wastewater treatment plant for the town of Kobylí within the Břeclavsko Project – reconstruction and construction of the water service infrastructure within the Dyje river basin. The Project was executed during 2007 - 2009 and in 2010, after the test run, the WWTP was put into the permanent operation. The plant meets the limits required for the treated effluent quality in compliance with the applicable both inland Czech national and European standards and the water regulation limits for Kobylí WWTP.  

The WWTP consists of the units of rough pretreatment with the storm water tank, mechanical pretreatment, combined biological stage for the low-load activation. The sludge service provides sludge treatment and hygiensation.

The waste water source consists of the municipal facilities. Recipient of the treated effluent is Trkmanka creek, joining the Svratka river.

 
Project:
Břeclavsko - reconstruction and construction of the water service infrastructure within the Dyje river basin "Břeclavsko Project - part C"- WWTP Kobylí - 2 420 PE
Project commencement:
2008
Locality:
CZ, Kobylí
Investor:
Vodovody a kanalizace Břeclav, a.s.
Scope of Project:
Construction of the Kobylí wastewater treatment plant (5400 PE). General delivery of the technological part, electrical equipment and Instrumentation.