KRÁLOVOPOLSKÁ RIA, a.s. participated in the construction of the new steam gas source 880 MW in the Počerady power plant through delivery of the 07 package – Natural gas regulating station. Construction of the new source was performed under management of the company ŠKODA PRAHA Invest as a general contractor.

Within this Project the company Královopolská RIA used its experience in construction of the HP connection, regulating station and MP industrial gas line in the Ledvice power plant.

Construction of the new gas power source with highly effective heat energy transformation to electric power provided a significant contribution to the environment as a cleaner power generation source.

 
Projekt:
Steam gas source 880 MW in the Počerady power plant - OB07 - Natural gas regulating station
Zahájení realizace:
2010
Lokalita:
CZ, Počerady
Investor:
ČEZ, a.s., Duhová 2/1444, 140 53 Praha 4
Předmět zakázky:
General delivery of the 07 Natural gas regulating station 190 000 Nm3/hr package and gas line for the steam gas source 880 MW in the Počerady power plant, including design documentation.